Judge Stops Arch Construction Near Cemetery
A federal court blocked the project over traffic delays and crane height issues, ruling the timeline was too aggressive for the National Park Service to manage.
By Pedro Tanaka ·

A federal judge in the Eastern District of Virginia issued a preliminary injunction on November 20, halting the administration's plans to build a triumphal arch near Arlington National Cemetery. The ruling prevents the National Park Service from beginning construction until the project undergoes further review. This decision marks the latest legal hurdle for the proposal, following a temporary block by a judge in Washington, D.C., earlier in the month.
The court found that the administration rushed the process, requiring the agency to bypass standard legal protocols to meet its schedule. Arlington County's board of supervisors brought the suit to stop the work. The county argued that the two to three year construction window would severely disrupt traffic through Memorial Circle. Daily commuters, police, fire, and rescue units serving Reagan National Airport and Arlington National Cemetery would face persistent delays.
The project involves an arch that would stand 150 feet taller than the Lincoln Memorial. During the hearing, the judge questioned the Park Service attorneys about the cranes required for such a structure. The attorneys stated that the agency had not yet issued bids for cranes, meaning they were not part of the current plan. The judge noted that crews would need cranes to build the arch, highlighting a gap in the agency's logistical planning.
Arlington County Board Chair Matt de Ferranti stated that local residents are concerned about the impact on the cemetery. He said, “Those are concerns Arlingtonians have shared with me. They don’t want a fanciful project that is gilded. Instead, they want the solemnity of appreciating our veterans.” The county contended that the administration failed to address the consequences of the project on the region before pushing for a start date.
The preliminary injunction stops the work for the time being. The National Park Service has the option to appeal the decision to a higher court. The arch project remains paused while the legal dispute continues. The ruling forces the agency to address traffic and air traffic concerns before it can restart the process.